AGO AG Energie + Anlagen was assigned a major order in the amount of about EUR 11 million

 

Erection of a cooling plant with a capacity of 7.5 MW including construction

Completion by October 2018

Project to be carried out in corporation with a construction company

 

 

Kulmbach, 6 September 2017: A notable automobile manufacturer assigned AGO AG Energie + Anlagen with the erection of a cooling plant with a total cooling capacity of 7.5 MW. The order for the construction of the building and the cooling plant amounts to about 11 million €. The project will be carried out in corporation between AGO AG Energie + Anlagen and a well-known construction company which will be responsible for the building construction. The project is sought to be completed by October 2018.

 

The turnkey cooling plant consists of 3 x 2.5 MW turbo core chillers with re-cooling units and piping, medium and low voltage system including transformers and instrumentation & control. The chillers will provide cooling energy with a temperature of 8/16°C for the factory.

 

„We’re pleased to have been awarded yet another major order in the field of decentralized energy supply. This is a clear success on the road of our diversification strategy setting a positive signal for the next fiscal year. We consider this a great opportunity to dynamically expand our business unit “plant engineering” and are already negotiating further orders of this kind“, says CEO Günther Hein.

 

The Board

 

 

 