BEW GmbH, Bayreuth

 

Delivery, assembly and commissioning of a cogeneration plant with a natural gas engine and a steam extraction system. The extracted heat is fed into the district heating system.

 

A stationary tube heat exchanger removes saturated steam from the existing steam network, converts it into hot water to feed it into the district heating network. The power control is carried out via the condensate backup in the heat exchanger.

 

  • Electrical capacity: 1.200 kW
  • Thermal capacity steam: 780 kg/h (4,2 bar / 160°C)
  • Thermal capacity warm water: 755 kW (10 bar / 90°C)
  • Thermal capacity: 7.000 kW
  • Design: AGO AG Energie + Anlagen
  • Client: BEW Bayreuth GmbH

 

 

CHP, steam station

 

Back

BEW GmbH, Bayreuth

 

Delivery, assembly and commissioning of a cogeneration plant with a natural gas engine and a steam extraction system. The extracted heat is fed into the district heating system.

 

A stationary tube heat exchanger removes saturated steam from the existing steam network, converts it into hot water to feed it into the district heating network. The power control is carried out via the condensate backup in the heat exchanger.

 

  • Electrical capacity: 1.200 kW
  • Thermal capacity steam: 780 kg/h (4,2 bar / 160°C)
  • Thermal capacity warm water: 755 kW (10 bar / 90°C)
  • Thermal capacity: 7.000 kW
  • Design: AGO AG Energie + Anlagen
  • Client: BEW Bayreuth GmbH

 

 